3.4.1
Unless otherwise notified by CDP to the Settlement Participants, the settlement schedule set out in Appendix 1 of Regulatory Notice 3.4.1 shall apply for Batch Settlement. If any activity set out in the settlement schedule is likely to be delayed, CDP shall inform Settlement Participants of the following matters:
(a) that the activity is likely to be delayed; and
(b) the estimated timing for the delayed activity.
CDP shall provide adequate time for Settlement Participants to carry out the activities set out in Appendix 1 of Regulatory Notice 3.4.1 and Settlement Participants shall carry out such activities by such time as stipulated by CDP.
Refer to Appendix 1 of Regulatory Notice 3.4.1.
Added on 10 December 201810 December 2018.